Dubai sports city

Akoya & Dubai Sports City Chilled Water Network

Our team served as the client’s trusted advisor, providing ongoing project status, contractor performance monitoring and review, and highlighting and mitigating project issues and risks.

Client

Emicool

Location

Dubai, UAE

Project Scale

170M AED, 40km

Leveraging our stakeholder collaboration skills to guide the client to success.

This underground chilled water pipe network project expanded Emicool’s chilled water service and enabled it to deliver 20,000 tonnes of refrigerated water from its district cooling plant in Motorcity to Akoya City via a new eight km pipeline.

Our team ensured engagement among all project stakeholders, including RTA, DEWA and Damac, as well as the Akoya City developer. We established a collaborative approach to successfully deliver the project on time, on budget and to the required quality standard.

Colliers Project Leaders were our trusted project advisors providing pertinent advice on managing design, construction, contractual, and commercial matters.”

Dr. Adib Moubadder

CEO, Emirates District Cooling (Emicool)